Client:
Amco
Project Description:
Ballast retainment and cess installation
Duration of works:
4 weeks - midweek

SCOPE

The site at Walk Mill comprised of a 10m high steep embankment that had a high ballast shoulder over a length of approximately 300m. This section of line was classed as “at risk” of having continual ESR/TSR due to potential alignment issues caused by the lack of a compliant cess and ballast retainment issues on the shoulder.

SCOPE

Amco approached TRS to design and construct a cess retention system and a safe cess walkway.

PROJECT

To hold back the cess and ballast we installed 7m long H-Piles at 1m centres  along the crest of the Down Cess. Between the H-Piles we used hardwood timber to retain the ballast.  We then introduced a safer cess walkway and also a new handrail and cable route to improve worker safety.

As the four week project was carried out at the same time as the Holme Tunnel Blockade, this restricted access to the Walk Mill site.  We therefore worked closely with the maintainer and shared a small access point five miles away.  This meant we had to transport all our materials during Saturday night possessions, and in sufficient quantities to keep our gangs busy during the week.

OUTCOME

The contract started and finished on time and we delivered it on budget and with zero accidents.

“This was a tricky scheme with the potential to go wrong, particularly with the access point so far away from the site. Credit to TRS, they managed it so well that it was never on my radar which allowed me to give full concentration to the Holme Tunnel Reconstruction”.

Dave Thomas, AMCO Senior Project Manager